Energized vs announced campus MW

Notes

Energized vs announced campus MW

One-line summary: Keep issuer "compute power," Epoch "IT power," and announced / offtake GW as separate units. Do not collapse SpaceX ~1.0 GW compute power with Epoch 1,286 MW IT or with unfetched Introl 2 GW / 555k. Campuses with no citable official MW stay blank.

The insight

"How many gigawatts of AI campus exist?" is three questions: what is energized on an independent tracker, what the issuer claims in its own unit, and what is only announced or leased. Mixing them invents a single capacity number the sources do not share.

Evidence

Retrieved energized vs claimed, as-of the 2026-08-27 clip (Epoch sat Jun 15, 2026 unless noted):

WhoEnergized (retrieved)Claimed / offtake onlyAs-of
colossus 1Epoch 340 MW IT, 230k chips (150/50/30 H100/H200/B200). Anthropic: >300 MW / >220k GPUs leased.Older All-In 220k/300 MW is the Anthropic line, not a new count. Grokipedia 200k H100 is stale.Epoch Aug 26 / sat Jun 15, 2026; Anthropic May 6, 2026
colossus 2Epoch 946 MW IT, 440k chips (110k B200 + 330k B300). Issuer first two clusters = 110k GB200 + 110k GB300.Combined issuer ~1.0 GW "compute power" vs Epoch 340+946 = 1,286 MW IT. Introl 2 GW / 555k (Jan 2026) is a contested vendor claim, not fetched.Issuer prospectus Jun 11, 2026; Epoch Jun 15 sat
microsoft-fairwaterWI-1 operational Jun 23, 2026; Atlanta "began operation in October." Network: "hundreds of thousands" of Blackwell GPUs.No official MW. Third-party 340 / 700 MW Atlanta figures were search-only — not used.MSFT Jun 23, 2026 + Fairwater feature
meta HyperionNot described as energized. "In advance of … coming online."5 GW IT announced Jul 13, 2026. CNBC "2 GW by 2030 / 5 GW ~2032" is search-only — not cited as fact.Meta + LED Jul 13, 2026
coreweave (fleet, not one campus)1.5 GW active power (Jun 30, 2026).~3.7 GW contracted (6/30); call-date 4.2 GW contracted (Aug 11); YE 2026 guide >1.85 GW; ≥8 GW by 2030.IR + Fool transcript
Anthropic offtakeColossus 1 lease as above.Amazon up to 5 GW, "nearly 1 GW … by end of 2026"; Google+Broadcom 5 GW from 2027.Anthropic May 6, 2026
Google as tenant—SpaceX FWP: ~110,000 NVIDIA GPUs, $920M/month Oct 2026–Jun 2029; delivery gate Sep 30, 2026. Facility not named.SEC FWP Jun 5, 2026
Amazon / Oracle / OpenAI campusesNo official campus MW or GPU counts retrieved this pass.Stargate / Ohio 8 GW (Bloomberg) left as search-only.Provenance miss

From 2026-08-27-xai-data-center-build-tempo-vs-peers-and-ai-campus-capacity.

Leave as announcement, not energized: Colossus II next phase ≥220k additional GB300 / >400 additional MW (Epoch already books most of that into the Jun 15 946 MW line); Epoch Q1 2027 1,531 MW IT / 722k chips / $58.0B is a projection; Microsoft WI-2 2028; Hyperion first-energize date not on the Meta page; SpaceX orbital "as early as 2028" is not terrestrial MW. From 2026-08-27-xai-data-center-build-tempo-vs-peers-and-ai-campus-capacity.

Contradictions / tensions

Open questions

  • Microsoft Fairwater MW? Amazon / Oracle / OpenAI official campus MW? Google 110k GPUs — which building? Official TVA order? MDEQ permit PDF? x.ai/colossus body (Cloudflare-blocked).